Wetlands & Valuation 18 November 2026 By Harihar.S, Registered Valuer

Pallikaranai Ramsar: High Court Disposes of Petitions, Petitioners to Approach the Supreme Court

On 18 November 2026 the Madras High Court disposed of thirteen writ petitions against the construction freeze within 1 km of the Pallikaranai marshland. The court declined to interfere with the National Green Tribunal's order or CMDA's Office Order 07/2025, and gave the petitioners liberty to approach the Supreme Court for the smaller interim zone proposed by the Wetlands Authority. The 1 km freeze therefore stays as it is. This page is based on the signed order itself. It sets out what the order says, what it leaves open, and what owners and buyers can do in the meantime.

Status today: the High Court held the petitions maintainable but refused to interfere with the impugned orders or to permit building approvals in the disputed zone. The 1 km freeze continues, and the Wetlands Authority's 128.19 ha interim zone is still only a proposal. Any change now has to come from the Supreme Court.

What the Order Is

The order was reserved on 11 November and delivered on 18 November 2026 by a First Division Bench of Chief Justice Sushrut Arvind Dharmadhikari and Justice G. Arul Murugan, in W.P. No. 7120 of 2026 and twelve connected petitions (neutral citation 2026:MHC:4601, 44 pages). The petitioners were CREDAI-Chennai and other developers, residents' associations, trusts and private patta landowners. They challenged three things: the NGT order of 24 September 2025 (O.A. No. 91 of 2023), CMDA Office Order 07/2025 of 9 October 2025, and, in one petition, the NCSCM interim map of 18 August 2026 that placed a Sholinganallur patta land inside the marsh boundary.

What the Court Decided

The Two Directions in Para 21

  1. Liberty to approach the Supreme Court. The petitioners may file applications in W.P.(C) No. 230 of 2001, or start fresh proceedings, to seek clarification, modification or permission to implement the revised interim zone of influence proposed by the Tamil Nadu State Wetland Authority, “if so advised”.
  2. Directions to the authorities. The Wetland Authority, the Directorate of Survey and Settlement and the NCSCM must complete the ground-truthing, boundary demarcation and statutory notification under the Wetlands (Conservation and Management) Rules, 2017, in line with the Supreme Court's directions.

No costs were ordered.

What the Order Is Not

The Supreme Court Timeline the Order Mentions

The order quotes the Supreme Court's order of 12 October 2026 in Anand Arya v. Union of India (W.P.(C) No. 304 of 2018, connected with the M.K. Balakrishnan matter). The Supreme Court noted Tamil Nadu's four-stage ground-truthing method (ground-truthing, cadastral superimposition, revenue record reconciliation and physical pillar demarcation) covering 28,898 waterbodies, directed other States to follow it, and allowed four months to complete the exercise. That is the clock to watch for the marsh boundary. How long the zone question takes after that is not stated in the order.

The Proposal the Supreme Court Would Be Asked to Accept

The Authority's revised status report of 1 October 2026, as recorded in the order, cut the interim zone from 3,474 hectares to 36 survey numbers covering 128.19 hectares that directly affect water inflow and drainage connectivity, after considering 23 landowner representations and historical satellite imagery. It proposed regulated construction there, subject to environmental safeguards and a No Objection Certificate from the District Level Wetlands Management Committee, instead of an absolute ban. Details are in our 24 October update. The petitioners' arguments are in our 11 November update.

What Is Still Undecided

What Owners and Buyers Can Do Now

How This Affects a Valuation Report

A report on a parcel near the marsh should record the survey number against the Ramsar boundary, the CMDA 1 km map and the proposed interim zone, and state that the interim zone is unresolved and has been left to the Supreme Court. The open question is a real uncertainty a willing buyer would weigh, and a report cannot predict how the Supreme Court will decide. I will say so plainly in the report.

Read the Order

The full 44-page judgment is available as a PDF: Madras High Court order, W.P. No. 7120 of 2026, 18 Nov 2026 (PDF). The operative part is paras 20 and 21 on pages 40–41.

Not sure where your plot stands?

Send me your village and survey number and I will check it against the CMDA map and the proposed interim zone, and tell you plainly where it stands.

This page is a plain-language summary of the Madras High Court order dated 18 November 2026 and is not legal advice. It was also reported by The Hindu. For anything with money or a deadline attached, please also speak to your advocate. I will update this page when there is a Supreme Court development.